According to a report from NIPNA, quoting Hengam Petrochemical's
public relations office, the cooling water line was activated as part of the
continuous efforts to launch the urea unit. This achievement signifies the
successful completion of the pre-commissioning process for the auxiliary
services associated with the unit.
Following the completion of the urea substation three months ago,
Hengam Petrochemical specialists have now completed the final component of the
auxiliary services necessary for the unit’s operation.
Out of the 15 essential utility and auxiliary services required to
launch the urea unit, the cooling water lines were the final piece of the
pre-commissioning puzzle.
With the completion and activation of these auxiliary services, and
the arrival of the synthesis reactor, Hengam urea will soon be seen at the
Assaluyeh energy hub.